Design, execution, and installation of several tanks for storage and potato processing Equipment.

Design, execution, and installation of several tanks for storage and potato processing Equipment.
#projectmanagement #processengineering #tank #design #execution #piping # #Storage #production #food #foodindustry #TeamRAP #rapgroup #raptronic #challenge #potato

Specifications

Client:
New processing potato factory

Industry:
Food Industry

Location:
Romania

Year/Duration:
2023-2024

Category:
Process Engineering

Project Manager
Adriana Stoian

Group companies Involved:
RAP TRONIC PROCESS ENGINEERING

Project description

Scope: Design, execution, and installation of several tanks for storage and potato processing Equipment:

Equipment

  • 1 tank – 55 m³
  • 2 tanks – 36 m³ each
  • 2 tanks – 5 m³ each

Pumps and Pipe Routes:

Approximately 500 linear meters (lm)

#Team RAP Challenge:
Inserting the processing and storage tanks into the production area