Client:
New processing potato factory
Industry:
Food Industry
Location:
Romania
Year/Duration:
2023-2024
Category:
Process Engineering
Project Manager
Adriana Stoian
Group companies Involved:
RAP TRONIC PROCESS ENGINEERING
Scope: Design, execution, and installation of several tanks for storage and potato processing Equipment:
Equipment
Pumps and Pipe Routes:
Approximately 500 linear meters (lm)
#Team RAP Challenge:
Inserting the processing and storage tanks into the production area